Wednesday, August 8, 2007

Back porch pour

Had more stone delivered for the porch area(s) that will need to be poured on Monday...while I was in town returning the rotary hammer, the driver dumped 22 tons of coarse rubble crusher run stone a little off target and right into the path that the last cement truck will need to take to reach the back porch area...I built up the 19'x6' porch area with several inches of stone and built the forms. It's tough to drive stakes into rock, the rotary hammer would have been handy, but I did it with the tamper bar instead.

What did I learn today? You have to be on site no matter what for deliveries unless you want to make more work for yourself.